Handover is when a finished unit passes to its owner. Snagging is the inspection before or at that point - finishes, fittings, installations - so that defects are written down and put right. The law does not lay out a snagging procedure. What it does set is how long the developer stays responsible.
What the developer is liable for
- Structural parts: ten years from the date of the building's completion certificate
- Installations - mechanical, electrical, plumbing and sewerage: one year from the date the unit is handed over to you
Both come from Law 6 of 2019, Article 40. If an owner will not take possession, the one-year period runs from the completion certificate instead, so putting off the handover does not extend it.
Escrow adds a guarantee. Once the developer has the completion certificate, the escrow agent keeps back 5% of the account and releases it a year after the units are registered in their buyers' names (Law 8 of 2007, Article 14); the Land Department describes it as a guarantee that defects will be dealt with.
At handover
Inspect before you sign that you have received the unit, list every defect in writing, and keep a copy of the list the developer acknowledges. The one-year period for installations starts at handover, not when you move in.
After completion the developer enters the project in the Land Department's permanent register, and the units sold are recorded in their buyers' names (Law 13 of 2008, Article 8).
Sources
- Law No. 6 of 2019 concerning ownership of jointly owned real property: https://dlp.dubai.gov.ae/Legislation%20Reference/2019/Law%20No.%20%286%29%20of%202019%20Concerning%20Ownership%20of%20Jointly%20Owned%20Real%20Property%20in%20the%20Emirate%20of%20Dubai.html
- Law No. 8 of 2007 concerning escrow accounts for real estate development: https://dlp.dubai.gov.ae/Legislation%20Reference/2007/Law%20No.%20%288%29%20of%202007.html
- Law No. 13 of 2008 regulating the interim real property register: https://dlp.dubai.gov.ae/Legislation%20Reference/2008/Law%20No.%20%2813%29%20of%202008.html
- Dubai Land Department - Frequently asked questions: https://dubailand.gov.ae/en/frequently-asked-questions/
Checklist
- An inspection before you sign for the unit
- Every defect listed, and the list acknowledged by the developer
- The handover date - the one-year period starts there
Talk to us about a property
Tell us what you are after - a viewing, the price, the payment plan, or what it would return - and the consultant who covers it replies.
- 01Send the form, or message us on WhatsApp
- 02We reply within one working day
- 03A viewing, or the figures you asked for
- 04We put your offer in and handle the paperwork